Sunday, January 9

T minus 3...

More finishing touches on the space today. The front was finally cemented up by Neil. We fired up one of the ovens and tested it by making scones. The bakers, Matt and I came up with a baking schedule for the opening day, We hired an assistant baker and an assistant finisher, I hired my first barista, hopefully hiring my second tomorrow, Ken came by to finalize a thing or two, and Melanie rocked the place by cleaning up a storm.

Tomorrow holds much more cleaning, emergency runs to Daroma and a preliminary inspection from the D.O.H.

There is still so much to do, I don't think it will all be done in time. I have more punch lists than I would like to admit.

I'm exhausted. but we are almost there...